Brogan Group worked with a dedicated Data Centre delivery partner that provides turnkey solutions to clients. The project involved the construction of a single 1-4 storey Central Administration Building and two 2-storey (with mezzanine) data centres.
Each data centre included data halls, admin blocks (comprising of offices, canteen, loading dock, storage and ancillary areas) and a variety of mechanical and electrical plant areas/structures.
Design & Installation
Brogan Group collaborated with the Contractor to devise a unique CAS solution to form The Atlas™ Loading Gantry to service the 2-storey data centres and allow large plant and equipment to be transferred into the buildings for the fit-out.
The Atlas™ loading gantry, is flexible and has a number of benefits over a traditional Scaffold Gantry, including having the ability to tie a number of hoists to the structure, quicker to erect, having a larger weight capacity and with a reduced number of ties to the building.
Equipment of various weights, shapes and sizes could be moved in using multiple methods; cranes, telehandlers and attached Goods Hoists.
A second Goods Hoist was installed external to the Client Administration Building in addition to internal and external Scaffolding being erected. A temporary sheeting was also installed, to offer protection from the elements in advance of the building envelope being fitted.