The design for BAM Construction's access requirements at Unison HQ, Euston Road includes a bespoke temporary roof and scaffold that has been fully erected and monoflexed to block F on all five floors. Scaffolds have also been erected at the back of the A2 elevation for stone works and a cantilevered hanging scaffold has been erected to the South East elevation for brick work.

 

 

 

 

 

 

 

 

 

 

In addition, access has been supplied for the restoration of the bell tower on the listed building with hoist towers and run off ramps installed at Block C also.

The completed project, due for completion in February, 2011 will provide accommodation for Unison's new Head Quarters.