Since securing the scaffolding package in February for the reconstruction of Finchley Memorial Hospital, we have now also been awarded the contract to supply hoists to the project.

The hoists will be used for the transportation of personnel and materials. 

The main contractor has awarded further works which will span the £26.2 million two-phased project.

The first place will see the construction of a new hospital building adjacent to the current facility, with the existing building being demolished under the second phase. 

Our hoist operatives are now on site at the north London hospital, with works due to complete in July 2012. 

Tags on this post: hospitals

Share

Enquiries

Get in touch for quotations and more information

Enquiry Form

You can get in touch using our contact form below.

To find out about how we process your data, please read our privacy policy.

Send